Liberty Hill Approves $2.48 Million City Park Parking Lot Project

Liberty Hill's City Council approved a $2.48 million City Park parking lot project on July 8, 2026. A city newsflash posted Aug. 13, 2026, said construction was underway, with completion expected in February 2027.

Saved approved version. Read the current story for the latest reviewed update.

What to know

The council unanimously approved the $2.48 million project and awarded the construction contract to Patin Construction; the project is to expand the park's total parking capacity to approximately 230 spaces. [1]

Parkland fee-in-lieu money supplies $1.5 million, tree mitigation funds add $662,000, and general fund reserves cover $319,119. [1]

A city newsflash posted Aug. 13, 2026, said construction was underway as the first phase of planned park improvements. [2]

Work covers site grading, drainage and utilities, paving, sidewalks, ADA ramps, lighting, landscaping, striping and signage. [2]

The city said the main lot is closed and visitors should use the Liberty Hill Swim Center lot; the park remains open. [2]